Works exempt from a building permit under the new RJUE in Portugal — Paulo Silva Silva, Lawyer

In brief

Since 1 October 2026, the following are exempt from both a building permit and prior notification, among others: maintenance works, interior works that do not change the exterior or affect structural stability (or that do, if backed by a structural design and a statement of responsibility), reconstruction works and works of minor planning relevance (Articles 6 and 6-A of the RJUE). The change that matters most: extensions are no longer exempt. And exempt does not mean unregulated — the council must be told at least five days before work starts, or a fine applies.

Date note. Updated on 8 November 2026, based on the consolidated version of the RJUE (Decree-Law No. 555/99) as amended by Decree-Law No. 108/2026, in force since 1 October 2026, and by Rectification Statement No. 29-A/2026/1. RJUE is the Portuguese Legal Regime for Urbanisation and Building.

Refitting a kitchen, replacing windows, building a garden annex, rebuilding an old house. The question is always the same: do I need the council? With the RJUE reform, the answer changed on points that matter — especially for anyone rebuilding or hoping to add floor area.

Which works are exempt from permit and prior notification

Article 6(1) of the RJUE lists the operations that need no prior control. Those most relevant to owners and investors:

WorksConditionProvision
Maintenance (restoration, repair, cleaning)Keep the building in its existing conditionArt. 6(1)(a); Art. 2(f)
Interior alterationsNo exterior change with impact (heights, façades, roofs) and no effect on stability — or, if stability is affected, with a structural design, a statement of responsibility and, where required, a seismic reinforcement design, filed with the notice of start of worksArt. 6(1)(b)
Minor planning relevanceList in Article 6-A (see below)Art. 6(1)(c)
Reconstruction of buildings or unitsRebuild every façade and the roof according to the last valid precedentArt. 6(1)(e); Art. 2(c)
Works preceded by a favourable prior information rulingA ruling covering all items in Art. 14(2)(a) to (f); does not cover use or change of useArt. 6(1)(h)
Demolition of illegal buildings—Art. 6(1)(i)
Maintenance of listed buildingsWith a favourable opinion from the heritage authorityArt. 6(1)(k)

Plot subdivisions (destaques) meeting the conditions of paragraphs 4 and 5 of the same article are also exempt — a topic that deserves its own analysis.

The big change: extensions are no longer exempt

Under the 2024 Simplex reform (Decree-Law No. 10/2024), exemption covered reconstruction and extension works that did not raise the façade height, even if they added floors or usable area. Decree-Law No. 108/2026 narrowed Article 6(1)(e) to reconstruction of buildings or units only.

Reconstruction now has a demanding definition: building works following total or partial demolition, according to the last valid precedent, which restore the formal composition of every façade — dimensions and the relationship between openings — together with projecting and recessed volumes and the roof (Article 2(c)). Changes to structural materials and corrections strictly needed for safety and health are allowed.

In practice, any increase in footprint, gross floor area, façade height or volume is an extension (Article 2(e)) and requires a permit or prior notification under Article 4. Anyone buying a ruin on the assumption of «rebuild and add a floor» without a procedure needs to redo the numbers.

Works of minor planning relevance: annexes, walls, solar panels and windows

Article 6-A(1) classes the following, among others, as works of minor planning relevance:

  • buildings, attached to the main building or not, up to 2.2 m high (or up to the ground-floor height of the main building), with a floor area of 10 m² or less and not bordering the public road (point a));
  • boundary walls up to 1.8 m not bordering the public road, and retaining walls up to 2 m or that do not significantly alter the terrain (point b));
  • garden greenhouses under 3 m high and up to 20 m² (point c));
  • small landscaping works around buildings that do not affect the public domain (point d));
  • leisure or recreational equipment linked to the main building, with a smaller area than the building (point e));
  • photovoltaic panels not exceeding the roof area or rising more than 1 m above it; wind generators up to 4 m above the building with a radius up to 1.5 m, subject to prior notice to the council (point g) and paragraph 5);
  • replacing exterior cladding, roofing or roof tiles with energy-efficient materials of identical exterior finish (point h));
  • replacing window frames with more energy-efficient ones, keeping the geometry, the volumetric relationship of the components and the exterior finish (point j)).

Windows are where the news is. Point j) now requires the frame geometry and volumetric relationship to be kept and, in return, also applies to properties located in protection zones of listed buildings or buildings being listed. The previous wording referred only to replacing the materials of openings.

The regime does not apply to listed buildings or buildings being listed, nor to properties within listed ensembles or sites; in protection zones, only window replacement escapes the exclusion (Article 6-A(2)). Those cases fall under Article 4(2)(d): a permit — or prior notification if there is a complete favourable prior information ruling (Article 4(4)(l)).

Each municipality may class other works as of minor relevance and set its own limits for annexes, walls and greenhouses in its regulations (Article 6-A(1)(i) and (3)). Swimming pools are not named in the law; they are usually treated as leisure equipment under point e), but this depends on the municipal regulations and on each council. Check the local rules before you build.

Exempt does not mean unregulated: what is still required

  • Inform the council at least five days before work starts, naming the person in charge of the works and filing the items required by the ministerial order (Article 80-A(1) and Article 6(12)). Only maintenance works carried out exclusively inside the building are excused (Article 80-A(3)).
  • Post a notice on site, visible from the public road, at least five days before work starts (Article 80-A(5)).
  • Comply with the municipal master plan, public-interest easements and restrictions, technical building rules and heritage rules: the exemption waives none of them and the works can always be inspected (Article 6(8)).
  • Pay the fees and, where applicable, provide a guarantee and make land transfers before the notice of start of works (Article 6(13)).
  • Start within one year: the notice of start of works lapses if work does not begin within that period (Article 80-A(6)).

Where the same project also includes works subject to permit or prior notification, the formalities for those do not prevent the exempt part from going ahead (Article 6(14)).

The cost of getting it wrong

Starting work without first informing the council is an administrative offence punishable by a fine of €500 to €100,000 for individuals and €1,500 to €250,000 for companies — Article 98(1)(c) and (4).

Treating as exempt a work that is not is worse. An extension carried out without a procedure is an operation without a title: a fine of €500 to €200,000 for individuals and €1,500 to €450,000 for companies — Article 98(1)(r) and (2) — on top of the measures to restore legality: embargo, legalisation or demolition (Articles 102 et seq.).

And the problem returns on sale: the buyer and the bank will ask for the title covering the existing floor area. See what the deed must state about the planning title.

Before you start: four checks

  1. Classify the works using the definitions in Article 2 — maintenance, alteration, reconstruction or extension. The boundary decides the procedure.
  2. Confirm the property status: listed, being listed, part of a listed ensemble or in a protection zone; and the local municipal regulations.
  3. Prepare the notice of start of works and the site notice, and keep proof of filing.
  4. Update the land register afterwards, where relevant: the property description can be updated by a declaration that works of minor planning relevance were carried out (Article 6-A(4)) — useful if you later sell.

Frequently asked questions

Do I need a permit for works inside my home?

No, as long as the works do not change the exterior (heights, façades, roofs) or affect structural stability. If they touch the structure, they remain exempt provided they are backed by a structural design and a statement of responsibility from a qualified professional and, where required, a seismic reinforcement design, filed with the notice of start of works (Article 6(1)(b) of the RJUE). The council must be informed at least five days beforehand, except for maintenance works carried out exclusively inside.

Can I replace my windows without a permit?

Yes, if the new frames improve energy efficiency and keep the geometry, the volumetric relationship of the components and the original exterior finish (Article 6-A(1)(j) of the RJUE). Since 1 October 2026 this also applies in protection zones of listed buildings, but not to listed buildings themselves or to listed ensembles or sites.

How large can an annex be without a permit?

Up to 10 m² of floor area, up to 2.2 m high (or up to the ground-floor height of the main building) and not bordering the public road (Article 6-A(1)(a) of the RJUE). Municipal regulations may set their own limits, so check them locally.

Does rebuilding an old house require a permit?

Reconstruction is exempt (Article 6(1)(e) of the RJUE), but only if it restores every façade and the roof according to the last valid precedent (Article 2(c)). Any increase in area, height or volume is an extension and requires a permit or prior notification.

Do I have to tell the council about exempt works?

As a rule, yes: at least five days before work starts, naming the person in charge (Article 80-A(1) of the RJUE). Without that notice, the fine ranges from €500 to €100,000 for individuals (Article 98(1)(c) and (4)).

The firm classifies works before they begin, prepares the notice of start of works and handles legalisation when the works have already been carried out. Book a meeting.

Read also

Legalising works without a permit: when it is possible and how to avoid demolition · The planning title in property sale contracts · Real estate lawyer in Cascais and Oeiras