Lapse does not operate automatically. It must be declared by the municipality, after a prior hearing of the interested party (Article 71(5) of the Legal Framework for Urbanisation and Building — RJUE). That hearing is the first line of defence, and it is the declaration that is challenged.
When a permit may lapse
Article 71 RJUE links lapse, among other situations, to failure to start or complete the works within the applicable time limits and to their abandonment. These time limits are counted under Article 279 of the Civil Code (Article 71(6) RJUE). Each ground has its own requirements, and that is where the defence is focused.
What is checked
- Whether the time limit relied on had in fact expired, counted from the correct date.
- Whether there were periods in which the works were stopped for reasons not attributable to the holder: stop-work order, interim relief, another pending procedure.
- Whether “abandonment” is proved, or merely presumed.
- Whether there was a prior hearing and whether the decision addresses what was argued in it.
- Which rules apply in time, for permits issued before the revision of the RJUE in force since 1 October 2026.
How to respond
- Response at the prior hearing, with evidence of activity on site and of interruptions not attributable to the holder.
- Court challenge to the declaration of lapse, with a request for suspension of effects where the stoppage causes serious harm.
- New application: the holder of a lapsed permit, prior notification or prior information may apply for a new permit or submit a new notification or prior information request, reusing documents from the earlier file under Article 72 RJUE. This route can run in parallel with the challenge.
Frequently asked questions
I am about to buy a building with licensed but stalled works. Am I at risk?
Yes, if the permit is close to lapsing or already subject to a declaration. It is checked before the contract: see Real estate due diligence.
The municipality declared the lapse without hearing me. Is the declaration valid?
The law requires a prior hearing. Its absence is a defect in the decision and a ground for challenge.
Related reading
- New RJUE confirmed for 1 October 2026: what changes in practice
- Planning refusal by the municipality
- Administrative and planning litigation
Areas covered
Support before the municipalities of Greater Lisbon — with particular proximity to Cascais, Oeiras, Sintra and the South Bank (Margem Sul) — and, by video conference, throughout the country.
Information and contact
Office at Lagoas Park, Building 7, in Oeiras. Meetings in person or by video conference, in Portuguese, English and Spanish.
Notice: before sharing documents, deadlines or the identity of the counterparty, please await confirmation that there is no conflict of interest and acceptance of the engagement. The information on this page is general in nature and does not constitute legal advice.