A stop-work order (embargo) halts the works while the municipality decides on their legal situation. It is a provisional measure, with grounds and duration limited by law, and it can be challenged.

When the municipality may stop the works

The mayor may order a stop to urbanisation, building or demolition works and to land remodelling carried out without the required permit, in breach of the approved project or of the conditions of the permit or prior notification, or in breach of the applicable rules (Article 102-B(1) RJUE). Notice is given to the person in charge of the works, to the permit holder and, where possible, to the owner (Article 102-B(2) RJUE).

How long it lasts

A stop-work order lapses once a final decision on the legal situation of the works is taken, or when the time limit set for that purpose expires. If no time limit was set, it lapses if no final decision is taken within six months, extendable once for the same period (Article 104 RJUE). The date of notification of the order and any extension must be tracked from day one.

What is checked

  • Whether the works had a permit and whether the stopped works are covered by it.
  • Whether the order identifies precisely what is stopped; stopping all works over a partial non-conformity is disproportionate.
  • Competence, notification and reasoning.
  • Whether the non-conformity can be cured with corrective or alteration works, or by legalisation.

How to respond

The stop-work order is challenged before the administrative court, as a rule within three months of notification (Articles 58 and 59 CPTA), with a request for suspension of effects where the stoppage causes serious harm. In parallel, regularisation is prepared, because the municipality’s next step may be a demolition order.

While it is in force, the order must be complied with: disregarding a planning enforcement measure constitutes the crime of disobedience (Article 100(1) RJUE).

Frequently asked questions

I own the works, but the order was served on the contractor. Can I respond?

Yes. The permit holder and the owner have their own interest; it is advisable to obtain a copy of the order and of the notice served on the site manager.

More than six months have passed without a decision. Can the works resume?

It depends on whether a time limit was set and whether it was extended. This is confirmed in the file before any work resumes.

Related reading

Areas covered

Support before the municipalities of Greater Lisbon — with particular proximity to Cascais, Oeiras, Sintra and the South Bank (Margem Sul) — and, by video conference, throughout the country.

Information and contact

Office at Lagoas Park, Building 7, in Oeiras. Meetings in person or by video conference, in Portuguese, English and Spanish.

Notice: before sharing documents, deadlines or the identity of the counterparty, please await confirmation that there is no conflict of interest and acceptance of the engagement. The information on this page is general in nature and does not constitute legal advice.

Information and contact

PT·EN
Book a callWhatsApp